Short answer: a shared fleet depot lets a fleet buy charging capacity instead of building a charging yard. Terawatt Infrastructure, one of the best-funded companies doing this in the US, has announced four airport-adjacent depots in robotaxi markets, two of them already operating. If you run a fleet near one of its markets, it is worth a quote before you commit capital to your own depot. If you own industrial land near an airport or a freight corridor, expect to hear from companies like this.
On November 12, 2026, Terawatt announced four new fleet charging depots: 6.6 MW in South San Francisco near SFO, 4.5 MW near Nashville International Airport, 3.5 MW in Miami's Design District and Wynwood area, and 7 MW near Dallas/Fort Worth International Airport. That is about 22 MW across the four. Two are operating now. Dallas and Miami are scheduled to go live this quarter. The company says the four together can charge more than 3,000 vehicles a day, and that it has nearly 30 more depots in construction or development across 16 US markets.
CEO and co-founder Neha Palmer put the pace plainly: "We have new sites up and running across the country, and more on the way in 2027."
The release did not name the fleets using the four sites. It did name Waymo and Lyft as Terawatt customers, and every one of the four cities is a market where Waymo runs or has announced robotaxi service. The release does say what three of them are for: the Nashville, Miami, and Dallas depots serve autonomous fleet operators, and South San Francisco supports one fleet's Bay Area operations. All four sit next to airports, where ride demand is dense and steady.
What a shared fleet depot is
Most fleets that electrify build their own depot. They own or lease the yard, apply to the utility for a bigger service, buy the chargers, and carry the whole project on their balance sheet. Our guide to phasing a fleet depot's electrical buildout walks through what that involves, and the utility step alone often takes longer than anything else.
Terawatt's model inverts that. It buys or leases land in places fleets need to be, secures the grid connection, builds the chargers, and runs the site. Fleets reserve space and pay for charging instead of owning the equipment. When the company raised more than $1 billion in 2022, led by Vision Ridge Partners, it described the pitch as letting fleet operators skip the capital spending and focus on their own operations. In June 2026 it added a five-year senior secured debt facility of up to $300 million ($150 million committed, a $150 million option), led by RBC Capital Markets, to buy and develop more depots.
That financing detail matters more than it looks. Banks lending against charging depots, rather than venture money alone, suggests the lenders were comfortable with the revenue outlook. It does not prove any single site is profitable, and the terms of the customer contracts behind it are not public.
From trucks to robotaxis
Terawatt's first operating site tells you where the company started. In April 2025 it opened a heavy-duty depot in Rancho Dominguez, California, about 12 miles from the ports of Los Angeles and Long Beach: 20 pull-through and bobtail DC fast-charging stalls, 7 MW, reservable, which the company said could serve up to 125 trucks a day. PepsiCo was announced as a user for last-mile delivery. The site opened later than first planned; early reporting had targeted mid-2024.
The November four are a different business. Compare the company's own numbers:
| Site | Opened or due | Grid capacity | Vehicles served |
|---|
| Rancho Dominguez, CA (heavy trucks) | April 2025 | 7 MW | Up to 125 trucks a day |
| South San Francisco, CA | Operating (Nov. 2026 announcement) | 6.6 MW | Not broken out per site |
| Nashville, TN | Operating (Nov. 2026 announcement) | 4.5 MW | Not broken out per site |
| Miami, FL | Due Q4 2026 | 3.5 MW | Not broken out per site |
| Dallas, TX | Due Q4 2026 | 7 MW | Not broken out per site |
| The November four combined | | About 22 MW | More than 3,000 vehicles a day |
The release names Dallas and Miami as the two still to open, so South San Francisco and Nashville are the two operating.
Do the division. The truck site works out to roughly 18 vehicles a day per megawatt of capacity. The November four work out to roughly 136 a day per megawatt, more than seven times as many. That is not a sign one site is better run. Mostly it is energy per vehicle. A heavy truck can need several hundred kilowatt-hours per visit. A robotaxi is a passenger car with a much smaller pack, so even a deep charge between shifts is a fraction of that, and the same grid connection can turn over far more of them. Both figures are the company's own ceilings, not measured use, so treat the ratio as directional.
For a depot developer, that difference is the whole business case. More vehicles per megawatt means more customers sharing the cost of the most expensive and slowest thing on the site, the utility connection. It also explains why airport-adjacent land in robotaxi cities is where this money is going right now, while heavy-truck charging, which needs megawatt-scale connections and has slower fleet adoption, builds more slowly. Our piece on megawatt truck charging covers what those sites demand.
Who should pay attention, and who can skip it
Fleet operators in or near Terawatt's markets. If you run delivery vans, rideshare, rental, or service vehicles and you have not committed to your own depot, get a quote for shared depot charging before you file a utility application. The comparison that matters is not the per-kWh price alone. It is that price against the full cost of owning a depot: the service upgrade, the chargers, the maintenance staff, and the year or more of waiting for the utility. Our charging-as-a-service contract terms guide lists what to pin down.
Fleets that need the vehicles parked at their own yard. Skip it, mostly. A shared depot works when vehicles can drive to it as part of the duty cycle. If your trucks are loaded overnight at your own dock and leave at dawn, deadheading to a depot 20 minutes away eats driver time and range every day. That math rarely favors the shared site.
Owners of industrial or flex land near airports, ports, and freight corridors. Pay attention. Depot developers are buying and leasing exactly this kind of site, and with nearly 30 depots in development they need more. A parcel with available grid capacity nearby is worth more to them than one without. Read our guide to what charging networks pay landowners before taking a first offer.
Retail and office property owners. Mostly skip it. A fleet depot is a fenced, high-power industrial use with traffic around the clock. It is not an amenity for your tenants, and it is a different deal from hosting public chargers.
Caveats
The four-site announcement is the company's own, and we read it through Charged EVs' report of the release (November 12, 2026) and other trade coverage; we did not review the original press release directly. The capacity figures, the 3,000-vehicles-a-day claim, and the depot pipeline are Terawatt's and were not independently checked. Some coverage dates the Dallas and Miami openings as Q4 2026 and the release says "this quarter"; those are the same window, but they are still targets, and Terawatt's first site opened months behind its original schedule.
No pricing, contract length, or reservation terms were disclosed, for these sites or for Rancho Dominguez. The vehicles-per-megawatt comparison uses the company's own capacity ceilings, not measured daily use. Which autonomous operator uses which depot is not stated; linking these sites to Waymo is inference from the cities, not a stated fact.
What to do now
If you run a fleet in one of these markets, ask a depot operator for:
- The price per kWh or per session, and whether it moves with the utility's rates.
- How reservations work, what happens if your vehicle arrives late, and what share of capacity is guaranteed to you.
- The uptime commitment and the remedy if chargers are down when your vehicles need them.
- Contract length and exit terms if you later build your own depot.
Then compare that against a real estimate for your own site, starting with the utility. Our guide to the utility service application explains what to ask for and how long it tends to take. For the wider choice of who owns the equipment, see own, operate, or turnkey.
Last factually verified: 2026-11-18. Sources: Terawatt Infrastructure's November 12, 2026 announcement as reported by Charged EVs (2026-11-12), read in full; the combined 22 MW and 3,000-vehicles-a-day figures and the Q4 timing as summarized in search results for Electrive (2026-11-16) and other trade coverage of the same release; Terawatt's June 2026 debt facility as summarized in search results for Electrive (2026-06-29), SFNet (2026-06-25), and Mercom; the Rancho Dominguez opening as summarized in search results for Electrek (2025-04-17), Charged EVs, and Fleet Equipment; Terawatt's 2022 funding round as reported by Charged EVs (2022-09-14), read in full; Waymo's market announcements as reported by TechCrunch. Pages we could not open directly were confirmed against at least two outlets. evcharginghelp.com is editorially independent and receives no compensation from any company named here.