TLDR
The Colorado Energy Office's fall Fleet-ZERO round for fleet charging opened November 16 and closes January 15, 2027, with questions due December 4. The Ohio Department of Transportation selected 40 new fast-charging sites backed by $31 million in federal NEVI funds and $10 million from private developers, each with at least four 150 kW ports. IONNA opened its 22-bay Westminster, California flagship and turned on Autocharge for Tesla drivers through the Presto app, and GM Energy Pass members with CCS-port EVs can now plug in and charge at Electrify America with no app or card. Tesla opened its first Texas Megacharger for the Semi, eight stalls of up to 1.2 MW in Mesquite. New Jersey's third electric school bus round funds 44 buses and 40 chargers for nearly $15 million.
Colorado's Fall Fleet Charging Grant Round Is Open Through January 15
The Colorado Energy Office opened the fall standard round of its Fleet-ZERO EV Charging Grant on November 16. Applications close at 5 p.m. Mountain on January 15, 2027. The program pays toward charging equipment for fleet vehicles.
The dates that matter. Questions are due by 5 p.m. Mountain on December 4, and the office says it will not answer questions one by one during a standard round. It expects to notify applicants within 60 days of the round closing. A separate medium- and heavy-duty corridor round runs on the same dates, and requests of $50,000 or less can be filed on a rolling basis all year.
The rule that catches people. A project finished before the office signs a grant agreement with you is not eligible. Per-port amounts depend on the charger type and power level; read the current program guide rather than a third-party summary, since the figures in circulation do not agree.
What this means for you. With the federal 30C charger tax credit ended for equipment placed in service after June 30, 2026, a state fleet grant like this one is now one of the larger sources of outside money for a Colorado depot. If you run vans, buses, or trucks in Colorado and plan to add chargers in 2027, hold your order until you have an agreement, and get your questions in by December 4. Plan a depot buildout that grows with the fleet.
Ohio Picks 40 More Federally Funded Fast-Charging Sites
The Ohio Department of Transportation selected 40 new fast-charging locations in its latest federal NEVI round, announced the week of November 17. The sites combine $31 million in federal funds with $10 million from private developers, and will sit at existing travel centers, gas stations, and restaurants.
What gets built. Each location will have at least four fast-charging ports with at least 150 kW available at every port. Construction is expected to start next year, with many sites expected to open by the end of 2027. The selected developers include 7-Eleven, Love's Travel Stops, Tesla, Red E Charging, Heartland Charging Services, and Universal EV, among others.
How it fits. This round follows Ohio's April selection of 64 sites for $51 million in NEVI funds. Last week we covered Pennsylvania's western round closing; Ohio is further along, moving from awards to construction.
What this means for you. If you own a travel center, gas station, or restaurant on an Ohio corridor and were not selected, check whether a funded site is planned near you before you commit to your own fast chargers, since a subsidized competitor down the road changes your numbers. For drivers, the 150 kW-per-port minimum means these sites should charge most cars at close to full speed. See Ohio's charging programs and utility rates.
Plug In and Go: IONNA Adds Tesla Autocharge, GM Gets Plug and Charge at Electrify America
IONNA. The automaker-backed network IONNA opened its first Rechargery Beacon, a flagship site in Westminster, California, on November 19. It has 22 charging bays, 12 with CCS1 connectors and 10 with NACS, rated at up to 400 kW, plus lounges, restrooms, and a cashierless store. The same week, the Presto charging app turned on Autocharge for Tesla drivers at IONNA sites: link your car and card in the app once, then plug in and the session starts. IONNA also announced benefits for eligible Stellantis owners starting in December.
GM and Electrify America. On November 17, GM said Chevrolet, Cadillac, and GMC EVs with a native CCS port can now use Plug and Charge at Electrify America stations through GM Energy Pass. Drivers enroll in Energy Pass in the brand app and add a payment method; GM says energy starts flowing within about 45 seconds of plugging in, based on its own testing. GM models with a native NACS port get the feature in early 2027.
What this means for you. Starting a fast-charge session is getting closer to the Tesla experience on every network, which removes one of the most common complaints about non-Tesla charging. If you drive a GM EV or a Tesla, set this up at home before a road trip, not at the charger. For site hosts, the networks that offer plug-in-and-go payment are the ones drivers will look for. See how drivers rate each fast-charging network.
Tesla Opens Its First Texas Megacharger for the Semi
Tesla opened its first public Megacharger in Texas on November 18: eight stalls of up to 1.2 MW each at a truck stop in Mesquite, east of Dallas. Electrek reports the opening brings Tesla's public Megacharger map to seven sites and 44 stalls. Tesla has not published prices, operating hours, or which fleets will use the site. In our October 12 issue, Pilot and Tesla opened their first Megacharger site in Ellabell, Georgia; Electrek notes Tesla remains well short of its earlier target of about 37 sites this year.
What this means for you. Megawatt charging is for heavy trucks, not parking lots. For most commercial properties, 150 to 400 kW is still the realistic ceiling. The sites to watch are truck stops and freight-corridor land near Dallas and other Semi markets, where a truck charging operator may come looking for power and space. If that is you, the utility service is the asset; find out what your feeder can supply before anyone asks. See who should plan for megawatt charging.
New Jersey Funds 44 More Electric School Buses and 40 Chargers
New Jersey awarded nearly $15 million in the third round of its Electric School Bus Grant Program, covering 44 battery-electric buses and 40 chargers, electrive and Automotive World reported November 18. Across three rounds, the program has now funded 145 electric school buses and 129 charging stations in the state. The program was created by 2022 legislation authorizing up to $45 million over three years.
What this means for you. For school districts and bus contractors, the chargers are often the slower part of the project, because the depot may need a bigger utility service. If your district won a bus, start the utility service request now so the chargers are ready when the bus arrives. See New Jersey's charging programs and utility rates.
New on evcharginghelp.com
State charging taxes. Ten states now tax electricity sold at public chargers, with Georgia starting January 1, 2027. Read the site host's guide.
Land lease offers. What charging networks actually pay landowners, and the clauses that matter as much as the rent. Read what landowners get paid.
Airport charging, both sides. For parking operators, why travelers and fleets need opposite chargers. Read the operator guide. For drivers, how to plan a week-long park. Read the trip plan.
Shared fleet depots. Terawatt's four new depots and what the shared hub model means for fleets. Read the analysis.
Lunar's bidirectional charger. The questions to ask before you wait for a 25 kW home charger with no price yet. Read what to ask.
By the Numbers
January 15, 2027: Close of Colorado's fall Fleet-ZERO standard round.
40: New fast-charging sites in Ohio's latest NEVI round, backed by $31 million in federal funds and $10 million in private money.
150 kW: The minimum power at every port on those Ohio sites.
22: Charging bays at IONNA's Westminster, California flagship.
About 45 seconds: GM's tested time from plugging in to energy flowing with Plug and Charge at Electrify America.
1.2 MW: The rating of each of the eight stalls at Tesla's Mesquite, Texas Megacharger.
129: Charging stations New Jersey's school bus program has funded across three rounds.
Sources: the Colorado Energy Office, Fleet-ZERO EV Charging Grant page (fall 2026 round), and Recharge Colorado; the Ohio Department of Transportation via Spectrum News (November 19, 2026), Richland Source, Government Technology, and WOWO; Axios and Electrek (Ohio's April 2026 round); Electrek and EV Charging Stations (IONNA Westminster and Tesla Autocharge, November 18 and 19, 2026); GM via Electrek, InsideEVs, and EVwire (November 17, 2026); Tesla via Electrek, electrive, and EVwire (Mesquite Megacharger, November 18 and 19, 2026); and electrive and Automotive World (New Jersey Electric School Bus Grant Program, November 18, 2026). evcharginghelp.com is editorially independent and receives no compensation from any company mentioned.