Wawa now has chargers at more than 280 of its roughly 1,200 stores, and in 2026 it started building its own branded DC fast chargers in Pennsylvania instead of only hosting someone else's network (Electrek, August 2026). Sheetz is rolling out up to 50 charging "Rechargeries" with IONNA by the end of the year. Pilot and Flying J passed 300 locations with GM and EVgo by summer 2026. Buc-ee's, Circle K, and 7-Eleven are all building out their own networks on different timelines. None of this is happening because fuel volumes are growing. ARKO Corp., a large convenience-store operator, reported first-quarter 2026 fuel revenue down 9.2 percent year over year and same-store gallons down 3.2 percent (10-Q filing; it attributed part of the drop to store closures and conversions, so it is one operator's result, not an industry total). Boston Consulting Group's widely cited 2019 projection put the share of U.S. fuel stations that could be unprofitable by 2035 at roughly 25 to 80 percent depending on the scenario, assuming they rely on gasoline alone.
Which Property Types Are Best Suited for EV Charging? mentions convenience stores once, in an infographic caption, and correctly flags them as a poor Level 2 fit. It never makes the case fuel retailers are actually building toward: DC fast charging paired with a store, not a parking amenity. This article covers that case directly, including the parts vendor content skips.
Why DC fast, not Level 2, is the right technology here
Session data settles this quickly. A 2026 study from the National Laboratory of the Rockies (formerly NREL) puts the median DC fast session at about 31 minutes almost everywhere, while median Level 2 sessions run about an hour or more even at retail sites. A convenience-store customer buying gas, coffee, and a sandwich is in and out in well under 15 minutes. At the roughly 25 miles of range per hour the Department of Energy cites for Level 2, that window adds about 5 miles, not enough to matter to most drivers. DC fast charging adds 100 to 200 miles in the same window, which is the whole point of stopping.
That is why every major fuel retailer moving into charging is building DC fast, not Level 2. It is also why the economics look nothing like a hotel or office install. DC Fast Charging ROI: Why the Math Is Different covers the full model; the short version below applies it to a fuel-retail site specifically.
What the big chains are actually building in 2026
- Wawa: chargers (Wawa-hosted Tesla Superchargers plus its own new branded DC fast stalls) at 280-plus of about 1,200 stores in 2026. Wawa hosts Tesla Superchargers at a large share of those stores, and it built out its first branded, non-Tesla charging through an Electrify America partnership, with Wawa-branded DC fast chargers planned at eight Pennsylvania stores (Electrek and CSP Daily News, 2026).
- Sheetz: partnered with IONNA (the automaker-backed charging joint venture) to add up to 50 "Rechargeries" by the end of 2026, starting in Springfield and Willoughby, Ohio, and Scranton, Pennsylvania.
- Pilot and Flying J: more than 300 locations and roughly 1,300 DC fast stalls across 40 states as of August 2026, built with GM and EVgo toward a commitment of up to 2,000 stalls at up to 500 travel centers. See also EVgo and GM flagship stations.
- Buc-ee's: charging hubs through a Mercedes-Benz partnership announced in 2023 to cover most Buc-ee's travel centers. The 400-station, 2,500-plus-charger by 2030 target belongs to Mercedes-Benz's whole North American network, not Buc-ee's alone, and the current number of open Buc-ee's hubs was not confirmed.
- Circle K: partnered with IONNA in April 2026 to deploy more than 350 sites, converting 85 existing charging locations and adding new ones, with 400 kW hardware supporting both CCS and NACS. First sites are expected by the end of 2026, with more in 2027.
- 7-Eleven: built its own 7Charge network, launched on CCS and CHAdeMO connectors; confirm current connector support before treating that as settled, since most new commercial DC fast deployments industry-wide had added NACS by 2026. Confirm its current states and store count with 7-Eleven before relying on either.
Two patterns stand out. First, almost every chain is partnering rather than self-building the charging network itself (IONNA, EVgo, Mercedes-Benz, Electrify America), which shifts most of the equipment and network-operations cost off the retailer's balance sheet. Second, nobody is doing this at more than a quarter of their footprint yet. This is a multi-year buildout at the largest chains, not a completed transition, which matters for how a smaller independent operator should read the trend: even the biggest players are still testing site economics, not confirming a settled playbook.
The in-store revenue case, and how much of it to trust
The argument fuel retailers make internally is that a charging customer is a different, more valuable customer than a gas customer: they dwell 20 to 45 minutes instead of 3 to 5, and that time gets spent on coffee, a made-to-order sandwich, or a grocery run instead of just a fill-up and a bathroom break. The National Association of Convenience Stores (NACS, the trade group, not the NACS charging connector referenced above) runs a Charging Analytics Program tracking roughly 8 million charging sessions a month across about 63 percent of U.S. chargers. Figures it presented in April 2025 put convenience-store charger utilization at 12.6 percent against a 17.6 percent industry-wide average (more recent figures were not found), meaning c-store chargers see less frequent use than the category overall even as retailers bet on them.
Be careful with the specific dollar-lift numbers circulating in trade coverage and vendor pitches, things like "EV drivers spend a dollar a minute" or fixed percentage lifts to foot traffic and revenue. Those figures come from charging-network and POS vendors with an obvious interest in the answer, not from an independent, retailer-wide study, and none of the major chains above have published audited basket-size data comparing charging customers to fuel customers at the same stores. Treat vendor-sourced lift claims as a plausible mechanism (a captive customer with 20-plus minutes to spend is a real opportunity) rather than a number to build a pro forma around. The honest input for your own model is your own store's existing basket size and margin per minute of dwell time, not an industry average someone is trying to sell you a charger with.
What it actually costs at a fuel-retail site
DC fast installs at commercial sites run $90,000 to $200,000 per port all in, with NEVI project costs reported in October 2024 working out to roughly $183,000 to $193,000 per port; a smaller two-port retail-anchor site without a highway-corridor grant typically lands in the $140,000-per-port range (around $280,000 total for two ports) because it cannot share electrical service and switchgear costs the way a larger site can (see the DC Fast Charging ROI model for the full cost breakdown). Demand charges, the utility's monthly fee for peak power draw, run $5 to $25 per kW depending on the utility, and they are the line every first-time DCFC operator underestimates: a single 150 kW port at peak draw can add well over a thousand dollars a month, and several thousand at higher-tariff utilities, before a single kWh is sold.
Two things specific to fuel-retail sites change the math from a generic commercial DCFC install. Most fuel-retail sites are not on a federally designated Alternative Fuel Corridor, so NEVI's 80 percent grant, which is what makes highway corridor DCFC pencil at all, usually does not apply; a c-store project has to work on a private-investment basis or with a network partner covering most of the hardware cost, which is exactly why Wawa, Sheetz, and Circle K are all using joint-venture partners instead of buying and owning chargers outright. And the federal 30C charger tax credit, which covered up to 30 percent of equipment and installation cost, ended for property placed in service after June 30, 2026, so any project starting now has to pencil on the full out-of-pocket cost.
The caveats vendor guides skip
Grid capacity is a real gating factor, not a formality. DC fast charging needs 480V three-phase service, which many existing fuel-retail sites were never wired for, and utility transformer or service upgrades are the single most common reason a project's cost and timeline blow past the initial estimate. Confirm available service capacity with your utility before you commit to a site, not after.
Charging stalls compete with fuel bays for the same footprint. A site that adds four DC fast stalls in its existing parking has usually given up parking spaces or circulation room that could otherwise serve fuel or quick-stop customers. That tradeoff is manageable at a large-format travel center like Pilot or Buc-ee's, where there is room to spare, and much tighter at a small urban or suburban c-store lot where every space already earns its keep.
Some of the "incremental" revenue may not be incremental. A driver who already stops at your store for gas and a coffee, and who now also charges there because you have chargers and a competitor down the street does not, is a retained customer, not new revenue. The clearest incremental case is the driver who would otherwise have driven past your store entirely and stops specifically because you have charging. That is a real and growing segment as EV ownership spreads, but it is smaller than "every charging session equals new revenue" framing suggests, and it is the number worth pressure-testing before you build.
Who should actually build now
The strongest case today is a high-traffic site on or near a designated highway corridor with existing three-phase electrical service or an inexpensive utility upgrade path, ideally with a network partner willing to cover most of the hardware cost in exchange for the site's traffic and dwell time. That describes the travel-center model Pilot, Buc-ee's, and the corridor-focused Wawa and Sheetz sites are pursuing. A small urban c-store without a nearby competitor doing the same thing, without corridor status, and without spare electrical capacity has a much harder case to make today: the Commercial ROI Snapshot will show whether your specific site's traffic and utility rate can carry an install before you spend anything on engineering, and Site Selection Fundamentals and How Many EV Chargers Does Your Property Need? cover the physical and sizing questions once the initial numbers look workable.
Last factually verified: October 19, 2026, against CSP Daily News and Electrek (2026) on Wawa's 280-plus charging stores and Electrify America-built branded chargers, trade coverage of the Sheetz-IONNA partnership (the 50-site end-of-2026 target; a current open-site count was not found) and the Circle K-IONNA partnership (April 2026: 350-plus sites, about 85 conversions, 400 kW, CCS and NACS, first sites by end of 2026), GMAuthority's August 2026 report of the Pilot, GM and EVgo network passing 300 locations, the 2023 Buc-ee's and Mercedes-Benz announcement (current open-hub count not found), 7-Eleven's 2023 7Charge launch coverage (current connector support not found), ARKO Corp.'s first-quarter 2026 10-Q (fuel revenue down 9.2 percent, same-store gallons down 3.2 percent), BCG's 2019 projection as reported by convenience.org, NACS and Transportation Energy Institute's Charging Analytics Program data presented in April 2025, the IRS Form 8911 instructions (revised December 2025) confirming 30C ends for property placed in service after June 30, 2026, the 80 percent NEVI federal share, and Paren's October 2024 NEVI per-port cost analysis. The Wawa hosted-Supercharger count and the Buc-ee's open-hub count in the earlier version could not be reproduced and were removed. The National Laboratory of the Rockies session-duration study, the install-cost and demand-charge ranges, and the DOE Level 2 range figure were not rechecked on this pass. The NACS Magazine, convenience.org, C-Store Dive, CleanTechnica, and CSP Daily News source pages were unreachable directly from this session's network; the figures drawn from them were cross-checked against independent trade coverage repeating the same underlying data before inclusion, and one figure that could not be reconciled this way (a combined Sheetz-and-Wawa charger count) was dropped rather than published unverified. This article also draws on this site's own DC Fast Charging ROI model (verified July 19, 2026) and Which Property Types Are Best Suited for EV Charging? (verified May 24, 2026) for install-cost, demand-charge, and dwell-time benchmarks.
evcharginghelp.com is editorially independent and receives no compensation from any company mentioned.
Corrections (October 3, 2026): This article previously cited NREL figures of about 50 minutes for an average Level 2 session and 28 minutes for DC fast. The current lab data (Desai, Steuteville and Johnson, Cell Reports Physical Science, August 2026) gives median DC fast sessions of about 31 minutes and median Level 2 sessions of about one hour or more at retail sites; the conclusion that Level 2 does not fit a short convenience-store stop is unchanged. It also said a sub-15-minute stop adds 15 to 25 miles on Level 2; at about 25 miles per hour it adds about 5.