Charging by the kWh or by the Minute? Weights-and-Measures Rules for EV Charging Site Hosts

The national model rule is clear: electricity sold as vehicle fuel is sold by the kWh, and a separate, disclosed fee can cover time spent occupying the space. Whether that is enforced against you depends on your state's weights-and-measures office, which decides whether to adopt NIST Handbook 44 section 3.40. California enforces kWh pricing and a displayed unit price on newer chargers, Wisconsin has been moving to adopt it (status unconfirmed), and other states run registration programs. The safe default is kWh for the energy, a separately labeled parking or idle fee for time, and a phone call to your state office before you launch.

By EV Charging Help editorial teamFor commercialNov 9, 2026
On this page

A charger that bills by the minute looks harmless: the driver pays for time, you collect revenue. The national model rule says that is not how electricity as a vehicle fuel is supposed to be sold. This article separates what is settled from what depends on your state, so you can set up billing before an inspector asks. It is not legal advice, and the pricing strategy side lives in Pricing Commercial EV Charging.

What is settled

NIST's guidance on EV fueling says electricity sold as a vehicle fuel is sold by the kilowatt-hour; NIST's materials also describe the megajoule as an allowed unit under the Handbook 130 model method-of-sale regulation. We did not read the exact Handbook 130 section. A charger cannot sell energy by units of time. You can, however, charge an additional fee for the time a vehicle occupies the space it needs to connect, such as an overstay fee once charging ends. NIST's answer is yes, provided the fee is properly disclosed, and the model text, as excerpted, expects those fees to be displayed and to appear on signs or advertising where they apply. Equipment that does both jobs has to keep the energy charge and the time charge clearly separate.

The equipment standard sits in NIST Handbook 44, section 3.40, which was a tentative code for years before it became a permanent code effective January 1, 2023 (per NIST materials seen in search results).

In plain terms: kWh for the energy, a separately labeled fee for time. A "per-minute" rate that is really the price of the electricity is the part that does not fit the model rule.

What depends on your state

Handbook 44 is a model, not federal law. NIST and the National Conference on Weights and Measures publish it, and each state decides whether to adopt it, which edition, and how hard to enforce. That is why you hear conflicting answers from vendors, who sell nationally.

The division of labor is also worth knowing. In most states, charger manufacturers are responsible for submitting models for National Type Evaluation Program (NTEP) certification. You, the owner, carry the state's installation and operation requirements: reporting the device, keeping it in service, and displaying prices correctly. So "is my hardware certified" is a question for your vendor; "have I told the state and priced correctly" is yours.

What we could confirm for four states:

StateWhat the sources sayWhat we could not confirm
CaliforniaRegulation 4 CCR section 4002.11 applies Handbook 44 section 3.40 with state changes. A computing EV charger must display a unit price in whole cents or tenths of a cent per kWh or per megajoule, or show that charging is free. DC chargers installed on or after January 1, 2023 and AC chargers installed on or after January 1, 2021 must comply on installation. Older DC units have until January 1, 2033; the Division of Measurement Standards' notice D-23-01, as excerpted, treats AC units installed before January 1, 2021 but placed in service after it as exempt until January 1, 2031, with the DC equivalent running to 2033.The exact answer in the Division's March 26, 2026 Q&A on whether a charger may bill by time alone.
WisconsinWisconsin Act 121 (2023) removed chargers that bill by the kWh from the "public utility" definition, which brought them under the state's weights-and-measures law. Rule CR 25-034 would amend ATCP 92 to adopt the 2024 Handbook 44, including section 3.40. A January 29, 2026 department memo described the rule as final draft.Whether the rule has been approved, cleared legislative review, and taken effect. Check the Wisconsin Administrative Register.
New YorkThe Bureau of Weights and Measures publishes an EV charger notification form (WM-15v, revised October 2024), so owners are expected to notify the state.Whether and how the state requires NTEP certification, and its Handbook 44 adoption status. Call the Bureau at 518-457-3146 or email agr.sm.WeightsandMeasures@agriculture.ny.gov.
Maryland, VermontMaryland requires a placed-in-service report for new or repaired devices and logs location, network, make, model, serial number and AC or DC type. Vermont applies NTEP and Handbook 44 to some private chargers offered to the public through apps.Detailed pricing rules in either state.

California is the only state above where we could list specific install-date cohorts. The practical lesson from the other rows is that registration and inspection programs are spreading even where the pricing rule is not yet written down.

The per-minute question

Some vendors say pure per-minute billing avoids certified-meter rules because no energy is being "sold." We did not find a regulator that says so. NIST's guidance, as excerpted, describes selling energy by units of time as not allowed, with a separate disclosed fee for time in the space. Vendor pages say the same, but a vendor's reading is not a regulator's, and we could not open NIST's page itself. Treat per-minute energy pricing as unproven in your state until the state office tells you otherwise in writing.

The limits of what we read: we could not read the California Division of Measurement Standards' March 2026 answer on time-only billing, and we found no state list of who has adopted section 3.40. If you are in a state not covered above, assume nothing and ask.

What to do before launch

  1. Price energy in kWh. Put any time-based charge on its own line, labeled as parking, overstay or idle, and say when it starts.
  2. Post the price where the driver sees it. NIST's model text expects additional fees on signs or advertising. California requires a displayed unit price on newer units. Your network software usually controls the on-screen part; ask the vendor how it shows both lines.
  3. Ask your vendor for the certificate, not the claim. Request the NTEP certificate of conformance number for the exact model you are buying, plus any state-specific approval, and put it in the purchase contract. Commissioning and handover is the point to collect it.
  4. Call your state weights-and-measures office. Ask three questions: Is Handbook 44 section 3.40 adopted? Do I register or report each charger? Is a time-based energy rate allowed? Write down the name and date.
  5. Check the software. Confirm the platform can bill kWh plus a separate time fee and can show both on the receipt. See Software Platforms for Commercial Charging.
  6. If a provider operates the site for you, find out who holds the registration and the pricing risk; the contract terms are covered in Own, Operate, or Turnkey?. If tenants are being billed, the separate resale question is in Charging Tenants for EV Electricity.

Leaving this to chance has a cost on both sides: a charger that cannot lawfully bill is a charger that earns nothing until it is fixed. For how pricing choices feed payback, see DC Fast Charging ROI.

Where we could not confirm

nist.gov, cdfa.ca.gov and chargepoint.com did not resolve from our research environment, so we read NIST's EV fueling guidance, the California regulation and notices, and the Wisconsin rulemaking record only through search-result excerpts, not the full documents. The California Division of Measurement Standards March 2026 Q&A, the New York form's contents and NTEP requirement, Wisconsin's final rule status, and any state-by-state adoption list are unconfirmed. Treat the table as a starting point and confirm the current text with your state office.

Last checked: November 9, 2026, against search excerpts of NIST's Electric Vehicle Fueling FAQs and Handbook 44 section 3.40 materials, the California Division of Measurement Standards EVSE regulation and notice D-23-01, the Wisconsin DATCP rulemaking record for CR 25-034 and 2023 Wisconsin Act 121, the New York Bureau of Weights and Measures EVSE notification form, and Maryland and Vermont agriculture department EV charger pages. The primary documents were not opened directly; see the section above, and confirm the current text with your state office.

evcharginghelp.com is editorially independent and receives no compensation from any company mentioned.

Sources & verificationLast verified Nov 9, 2026

Sources are cited inline where each figure appears. We re-check the numbers when incentive amounts, regulations, or product availability change.

Last updated Nov 9, 2026

ShareLinkedInXEmail
Keep reading
For commercial

Can a Landlord or Site Host Charge for EV Charging Electricity? Resale and Submetering Rules

Most states treat a business that sells EV charging as a service, not as a regulated electric utility, and that is the legal footing for charging by the kWh. The risk sits at the edges: apartment submetering, where the Massachusetts DPU says it is prohibited and New York and Pennsylvania cap what a tenant can be billed, plus tenant-charging statutes such as Illinois and California. Ohio's April 2026 Supreme Court ruling made a third-party electricity reseller a public utility, but it does not mention EV charging. Structure the deal as a charging service, price it at or near cost where a cap might apply, and confirm your state before billing anyone.

Updated Nov 20268 min read
For commercial

ADA Requirements for EV Charging Stations

There is no EV-specific federal accessibility standard in force. Commercial EV charging must comply with the 2010 ADA Standards as applied to fixed elements, operable parts, and accessible routes. The U.S. Access Board published proposed EV-specific guidelines (NPRM, September 2024), but it moved that rulemaking to inactive status on September 4, 2025, so no EVSE-specific federal scoping rule is in force. This article separates what current law requires, what the Access Board recommends as nonbinding technical assistance, and what the inactive proposal contained.

Updated Oct 202610 min read
For commercial

Adding NACS Connectors to Existing CCS Chargers: A Site Host's Decision Guide

If you own CCS-only DC fast chargers, the realistic way to add NACS is to swap a cable or a cabinet on some stalls, not to rebuild the site. Whether a swap is available depends on the charger model: ChargePoint says most of its stations have modular cables, and InCharge sells a cable-swap kit for two of its own charger lines. No vendor we found publishes a price, so budget from a written quote. Keep CCS on enough stalls to serve the installed base and to satisfy funding rules: federal NEVI rules require at least one permanently attached CCS1 connector per fast-charging port, and California's CALeVIP Window 2 requires at least half of a site's ports to be CCS and does not fund replacement installations. What happens to a charger's safety listing when a connector is changed is a question for the manufacturer in writing, because we found no primary source that answers it.

Updated Nov 202610 min read

Want the complete commercial guide?

The Commercial Charging Playbook covers evaluating, planning, and operating EV charging, including the funding programs that can cover most of the cost.

The Weekly EV Charging Briefing

One email a week. Just EV news that matters.

By subscribing you agree to our Privacy Policy. Unsubscribe any time.