What you get
- Why the wires side, not the chargers, is the critical path, with dated timeline anchors from utility application to energization.
- Which queue you are actually in, and when generation-interconnection or FERC rules apply on top of a plain service request.
- Who orders the transformer under each ownership case, and what 2026 lead times of three to nine months for catalog units do to a schedule.
- The 2026 funding map after the 30C sunset and the NEVI repurposing, including which flagship utility make-ready windows have closed.
- California's deadline machine: the 125-business-day energization target, the multi-year upstream maximums, and the two interim-capacity tools that are not the same thing.
How it was made
Second edition, re-verified against the indexed text of primary sources on September 4, 2026, with 72 claim-level endnotes that carry retrieval dates.
Read the full report
Free to read online. One email unlocks every report in the library for 90 days.
One email, 90 days of access to every report in the library, and the short weekly EV charging briefing you can drop any time.
From the report · The short version
Read the opening
The wires side, not the chargers, is the critical path. Published anchors for DC fast-charging projects run from roughly 6 to 24 months between utility application and energization, and every one of those anchors is either dated or program-specific (Exhibit 04). Where a circuit or substation upgrade is triggered, the CPUC's own maximum timelines for that work run from about two to nine years (Exhibit 08). Almost every schedule disaster traces to serializing work that could have run in parallel.
You are in the load queue, not the generation queue. A charging site is a new-service or upgraded-service request under the utility's line-extension and service rules. Utility or state generation-interconnection rules apply in addition only if you add solar or storage that operates in parallel with the grid; FERC procedures apply only where the interconnecting facilities sit under a FERC-jurisdictional open-access transmission tariff and are used for wholesale sales. A non-export battery may take a lighter path at some utilities, but that is utility-specific and configuration-specific, never automatic (Exhibit 03).
The full report continues with 18 more sections.
Get the full reportWho it is for
- Developers, contractors, and electricians scoping a new or upgraded utility service
- Fleet operators and site hosts planning around transformer lead times and utility deadlines
- Consultants, network operators, and municipalities tracking make-ready programs and federal funding after the 2026 reset
What is inside
- 01The short version
- 02The operator playbook
- 03Checklist and responsibility matrix
- 04Which process you are actually in
- 05The pipeline, drawn to time
- 06The study, and what you hand over
- 07Service paths and the four boundaries
- 08Screening: maps and written confirmations
- 09California's deadline machine
- 10The transformer clock
- 11Make-ready: how the money works
- 12Program status board
- 13The federal money after the 2026 reset
- 14Deadline radar
- 15Risk register
- 16Case notes, properly dated
- 17Glossary
- 18Data freshness, soft numbers, revision record
- 19Endnotes and sources
This document is educational reference, not engineering or legal advice.